It's been a few weeks and the back end is taking shape.  The rear has almost been completed and right now I'm in the process of welding it to the back of the sub and strengthening it up.

One of the most time consuming parts to make were the bearing and water seal brackets.  Each one was designed to scale on the computer to be sure that it would fit, and work, inside the 65 mm by 65 mm square tube (blue steel in the back of the photo).
20/04/2015

The elevator shaft tack welded in place.
21/04/2015

21/04/2015

The cable wheels that will guide the 5 mm diameter nylon cord to both the rudder and elevator shafts.
22/04/2015

22/04/2015

Testing the rudder and elevator pulleys with string.
24/04/2015

24/04/2015

Welding it all together.  Seeing as I don't have the right welder for aluminium I had the motor housing welded for me locally. 

22/04/2015

23/04/2015

23/03/2015

06/05/2015

06/05/2015

A video of the motor and rudder being tested.


Next post will be on the whole lot being welded to the rear of the sub and being sealed.